Invalid drainage and construction damaged nearby houses since 2014 must complete its mitigation quickly!

Underground Pipe Culverts from IJM Trehaus site on the left and nearby pond on the right

Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project. 
Approximate Coordinates : 5°20'38.47"N,100°16'52.82"E
Reported  in August 2016. Photos taken in November 2016 and 2014 by Penang Forum
PHW Report 




https://hillclearinginpenang.ushahidi.io/views/map

Sources: Penang Hills Watch (PHW) | Penang Forum

Hill clearing activity by IJM Trehaus Project


Clearing and construction for a condo and semi-detached housing project, Trehaus, reported in http://anilnetto.com/ 26 Aug 2016. Photo taken in 2014 ...

IJM sign-boards
Behind BJ Cove houses at Lintang Bukit Jambul 1 is an IJM Trehaus Project.

 

Two invalid pipe culverts formed sinkholes at BJ Cove houses


Originally, there were two natural rivers/streams from the IJM Trehaus site and a nearby pond. No proper drainage system was implemented when housing development started, only two invalid hidden underground pipe culverts were built to channel the waters from the Bukit Jambul hill to Relau district.

The invalid underground pipe culvert from the IJM Trehaus project directly converged at BJ Cove houses from another invalid underground  pipe culvert from a nearby pond were burst, caused soil erosion, house slabs collapsed, multiple wall cracks, PBA water pipe burst, floods, sinkholes (by two pipe culverts converged in red) and damaged  to  BJ Cove houses due to blockages of waters whenever rains and because of lack of drainage system there.  The sinkhole which later converted into a manhole by IJM,  is a clear sign of soil erosion under the ground.

Underground Pipe Culverts from IJM Trehaus site on the left and nearby pond on the right

It is a common sense that waters from the natural rivers or streams are natually running, seeped  through underground even the surface is covered by land-filled soil or with man made culverts.

Therefore, damages to houses were caused by severe soil erosion due to water movement under the road and buildings. 

The following is an invalid underground pipe culvert from the IJM Trehaus site behind BJ Cove houses at Lintang Bukit Jambul 1:


IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses

IJM modifying/constructing their underground pipe Culvert in 2014 to BJ Cove Houses

IJM Underground Pipe Culvert to BJ Cove Houses




IJM Underground Pipe Culvert to BJ Cove Houses
Waters gushing down from IJM Trehaus site to BJ Cove houses:

Waters flow from IJM Trehaus to BJ Cove houses
 

Waters gushing down from IJM Trehaus site to BJ Cove houses




Waters from IJM site stucked at behind BJ Cove houses

The nearby pond besides IJM Trehaus site:

IJM Hill cutting and hill Clearing 2014

Serious Drainage Issues


The Department of Irrigation and Drainage (DID or JPS) has just started in September 2017 constructing the drain from the pond to divert waters:

A drain under construction by JPS to divert waters from the nearby pond
Drain waters flow plan under construction by JPS to divert waters from the nearby pond

 Letter from Penang Dept of Irrigation and Drainage (DID or JPS) in 2015 blamed IJM  failure to comply with sedement control plan (ESCP) when its Trehaus started in 2014.



Clearly, the underground pipe culverts leaked and waters seeped through the ground and multiple cracks,  as it did not happen immediately but over a period of time!




Developers dishonored directives/letters issued by Penang City Council (MBPP - Majlis Perbandaran Pulau Pinang) in 2015 to rectify the damaged house






Developers have not honored their committments to rectify the damages despite  acknowledged their liability as per letters from Worldwide Venture Sdn Bhd, an subsidiary of IJM Land since 2014!


 
 


Despite the underground pipe culverts declared invalid by JPS and the Penang City Council's (Majlis Perbandaran Pulau Pinang, i.e. MBPP) issued stop work orders directing the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015 (as per the above attached letters), multiple wall cracks, slabs collapsed, PBA water pipes burst, leakage charges, damaging ceiling, electrical DB board, and tiles fallen, broken/popped up,  are still pending settlement and remedial works to be carried out by parties responsible for the damages since 2014 !!



IJM Land only started in December 2017 constructing new drainage to divert waters from Trehaus Site to the pond:


Pictures show IJM only started in December 2017 constructing drainage system to divert waters to the nearby pond



It is important that the pound should be made a Dried pond instead of existing wet pond on the following reasons:

i) The area was originally a natural rivers/streams where waters will still be naturally running, seeped through underground even when the underground culverts are to be closed/abandoned later.

ii) More waters are being diverted from the IJM site to the pond


 

However, damaged houses are still pending, not being rectified to date !

Damages appeared after IJM began construction works in 2014, like hill clearing, rock-blasting, piling and digging culvert at Trehaus site.  As a result, sinkholes appeared, floods, waters seepage through multiple cracks on the ground, walls, tiles fallen from roofs and popped up from the ground due to vibration from rock-blasting and piling for the building.

 
Sinkhole converted to manholes (2 in cycles) at BJ Cove houses are visible from the top of IJM Trehasu site

Pictures showing floods, sinkholes at Lintang Bukit Jambul 1, 11900 Penang,  damaged to BJ Cove houses, cracks, waters leakages seeped through the cracks, slabs collapsed, ceilings & tiles broken & fallen, electrical DB board explosion, etc caused by severe soil erosion due to water movement under the road and buildings. The underground pipe leaked and waters seeped through the cracks!


Sinkhole at BJ Cove house no. 20

IJM converted the sinkhole into a manhole waters from their underground pipe culvert at Trehaus

Sinkhole at house 20 is covered up by IJM's underground pipe culvert from  IJM Trehaus

IJM converting the sinkhole at BJ Cove no. 20

 



 

Truths Be Told:


 The truths be told,  as echoed, reinforced and justified by recent events in  Penang floods on 15th Sept 2017,  Landslides in Tanjung Bungah on 21 October 2017 .... see more on links to following reports:

Hills, landslides, floods and damaged houses ...

Penang landslides & flooding are natural disasters man-made...  

Penang floods and landslides, looking beyound natural causes!

Penang landslide, whose faults?

Penang Paya Terubong Residents living under shadow of fear!

Penang landslide tragedy, why it happened?  

PAC blamed Penang Island City Council (MBPP) for failing to enforce laws on hillside development  

 

We demand immediate enforcement & Actions:

 

1. The parties responsible must quickly without further delays, without condition to settle the claims and start the remedial works to the damaged houses, as both JPS has declared underground pipe culverts invalid and  MBPP has  issued stop work orders directed the developers, Worldwide Venture Sdn Bhd, a subsidiary of IJM Land to rectify the damages within 1 and 2 weeks time since 2015!


2. Enforce IJM's & MBPP' Letters/Stop-work Orders (attached in above), and divert waters from the two invalid underground pipe culverts deemed illegal at the IJM Trehaus site and nearby ponds which must be closed and grouted as a long term solution to the problems. 

 

3. Enforce a fresh cease and desist to stop work of IJM Trehaus construction project until the structural damages to house at 20 Lintang Bukit Jambul 1, BJ Cove have been resolved and settled the claim for damages and distress caused by the fear and danger of living in the house, without further delays and the suffering more than three and half years since 2014.  Repairs and remedial works must start promptly as more damages and suffering will fellow!

 

4. Beef up the enforcement and accountability not just in government agencies but also in professional bodies, like the Board Of Engineers Malaysia (BEM),  the Institute of Engineers Malaysia (IEM), etc to uphold the professional ethics, integrity and standards, to ensure public safety of the buildings and people life.

 

5. The pond must be made a Dried pond for waters to flow out smoothly, because there was originally two natural rivers/streams in the area where waters will still be running/seeping through naturally under the ground even if two culverts are closed as more waters are diverting from IJM Trehaus site to the pond.

 

 6.  Now, drain waters from IJM site are being channeled back their underground pipe culvert flowing to BJ Cove houses at Lintang Bukit Jambul 1 where a manhole next to house no. 20 constructed by IJM  is not closed despite it has been declared invalid and illegal by JPS!  This is a great concern to residents at BJ  Cove houses. We want JPS and MPPP to close & grout the manhole promptly.

 

7. Damaged house owners firmly reserve all their rights to take all necessary legal steps against those responsible exclusion their liabilities.

 


Findings from Penang Forum 

Dr Kam, a scientist, focused on expansion of impermeable surface area (caused by ill­ planned development and replacing natural ground cover such as hills, fields and trees that act as a water ­absorbing sponge) and soil erosion and landslides (caused by cutting and development in hill areas) as two factors that need special attention.

She quoted Datuk Kam U Tee, the Penang Water Authority general manager (1973~­90), as having correctly explained the Penang floods of October 2008, as follows: the floods were caused by conversion of the Paya Terubong and Bayan Baru valleys into “concrete aprons that do not retain water. The water immediately flows into streams causing flash floods even with moderate rainfall. Because of hill­cutting activities, the flowing water causes erosion of the slopes which carries mud and silt into the river beds”. ( The Star, Oct 24, 2008).


See more  ....
 




Credits - Slides presented by Environmental, health and safety consultant Aziz Noor, and scientist Dr Kam Suan Pheng at the Penang Forum event on Oct 29, 2017

See more ....



Practise true CAT for Sustainable Development

  • Penang government must provide a COMPETENT flood mitigation plan for the state starting with a comprehensive Drainage Master Plan Study and not slogan.

  • The Penang government has to be ACCOUNTABLE to the people and not private developers. In other words, ‘Politicians should be ‘wakil rakyat’ and not ‘wakil pemaju’. If certain waterways and catchment areas have to be gazetted as permanent drainage and storage areas, then so be it. 

  • The safety and well-being of the Rakyat has to come first.  In the interest of  TRANSPARENCY, Penang has to launch an inquiry into how the local council approved property developments on slopes without adequate slope protection.

 See more ...

1. Wanted: Leaders who listen !
2. Sustainable Development in Penang
3. Call to reassess Penang hillside projects, councillor addresses full council meeting of MBPP
4. Penang landslide, whose faults?



Related Links:

Watch "Slope Stability" on YouTube


https://youtu.be/2wT2he6Numk

Penang MP rapped for asking for allocation while rejecting Budget ...

KUALA LUMPUR: A Penang Opposition lawmaker was rapped for voting ... Budget 2018 yet seeking an allocation for flood mitigation projects.

RM150mil for flood mitigation projects - The Star Online


A tempest flays the north

GEORGE TOWN: When the storm hit, everyone in the north prayed it would soon blow over.Penang flood: Precautionary power cuts in place as waters rise

Penang paralysed by floods - Nation



Irked residents to hold meeting with state representatives on Penang ...



https://youtu.be/n2vO-nsZxkY

Damaged houses to be repaired - Metro News

Rep: Redevelop village to solve recurring erosion - Metro News

Residents prefer affected houses to be torn down manually

Bruised in sinkhole fall at home - Nation

Penang CM must stop blaming past govt for problems

Cracks in homes force seven Penang families to flee - Nation

Here's the proof — federal govt gave only RM443mil for flood mitigation

Former councillors claim Penang government abuse caused floods

PAS claims graft caused floods in Penang | Malaysia

Penang pays high price in storm havoc - Nation

Up to the chest in water, up to the neck with the excuses - Nation

Dept: Typhoon Doksuri caused erratic weather across Penang ...

Rapid development in Penang root cause of massive flash floods ...

Admit failure in solving floods and stop giving excuses, Penang govt told

Deluge brings chaos to northern states - Metro New

Penang floods: Body of missing woman found in Bukit Jambul river

Updated) Penang flash floods claim a life, second death due to floods ...

https://www.nst.com.my/.../updated-penang-flash-floods-claim-life-second-death-due-...
Sep 16, 2017 - ... Noor Afidah Yahunas, 30, who fell from her motorcycle into a culvert in ... by rescuers in a river near Bukit Jambul about 7.45am today, nearly 24 ... to lose balance and fall off, before she was swept away by strong currents.

Boast to end floods rings hollow - Nation

Anti-flood plan in pipeline - Metro News 

Chant: Set up unit to monitor hill projects - Nation

CAP: Halt projects in flood-prone areas until wet spell ends - Nation ...

Penang mayor Maimunah quits job to accept UN post


Hiking trail in awful condition - Metro News

Clogged drains main cause of floods - Metro News

 

  Narrow drains contribute to flooding

 The narrow drainage system which Chua claims results in flooding in the area.

 


Related posts:


Cracked drain causes road cave-in, house nearby on brink of callapse

https://youtu.be/9yXuW1pdrt4


MBPP, contractor, engineers and DOSH named as responsible in fatal Penang landslide

Kudos to Deputy Chief Minister I Datuk Ahmad Zakiyuddin for holding the four parties accountable for the Bukit Kukus landslide tragedy. The inquiry still begs a lot of questions, e.g. why was the contract given to Yuta Maju from Terengganu? Could the accident have been prevented if a proper EIA was done? It is not just a "bureaucratic hurdle" but supposed to identify risks and advise mitigation. If the authorities wish to go on with the project, it is not too late to commissi...
See more


 “This is no simple incident as nine deaths resulted from it. Very stern action must be taken against the MBPP, and that includes strong disciplinary action against the mayor and officers responsible.

“Otherwise, it will be business-as-usual in the MBPP as the officers will be allowed to go scot-free with impunity.



   Come together to save our state - Letters | The Star Online

 


Landslide nation, Malaysia ranks highly for landslides 

A drone picture of the collapsed beams along Jalan Tun Sardon leading to Balik Pulau on the left while Jalan Paya Terubong on the ri...
Consultant gets show-cause letter for ‘overlooking hilltop stream’ GEORGE TOWN: The consultant of the Bukit Kukus Paired Road project...


Action taken over irregularities at Bukit Kukus paired road project Penang

https://youtu.be/dMF95t2gXzg
Malaysia’s Penang Island has undergone massive development since the 1960s, a process that continues today with plans for transit and land-...

 

Huge landslide in Tg Bungah hill


Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year. GEORGE..

 

Fake Awards Scam for Penang Island City Council, Seberang Perai Municipal Council ! 

 

Home locked by Penang City Council over RM468 paltry arrears of assessment 

How to measure a politician?
Use technology to learn more about them before casting your vote Cheah taking a wefie with Tanjung Bungah assemblyman Teh Yee Cheu (be...


 Wanted: Leaders who listen !
Turning a blind eye: The grumblings over exposed hills are growing louder but little is being done to rectify the situation   G...


It’s hard to deny when the effects of climate change are all around us  Andrew Sheng says that from increasingly intense hurricanes t...


Why did MBPP approve the Tanjung Bungah development project? Read more at https://www.malaysiakini.com/letters/399357#qbRd534yu1JfC551....


https://youtu.be/kslhytLg-Wc Hills, landslides and floods: What to do?   The mega floods in Penang which followed the landslide...


Becoming bald: A view of the clearing work seen at Bukit Relau which was visible from the Penang Bridge in November last year. GEORGE..


Choong (in white) surveying the deforested hillslope next to Majestic Heights. PENANG MCA has raised concerns about the safety of the r...


Wet, wet woes: (Above) Bukit Jambul is flooded once again after an evening downpour. Firemen installing a pump to draw floodwater...


Council should not bow to development or political pressure, says city councilor, Khoo ‘Politicians should be ‘wakil rakyat’ and n...


Seeking solutions: Penang Forum member and soil expert Dr Kam Suan Pheng giving her views during the dialogue session themed ‘Penang Fl...

(From left) Dr Kam will deliver a talk on ‘Understanding the Causes of Floods and Seeking Solutions. State assemblymen expressing inter...


https://youtu.be/4qaOB1n5tgA GEORGE TOWN: The Penang Island City Council has lodged a police report against the consultant of the aff...


Speaking out: Penang Forum members protesting outside the CAP office in George Town. Don’t just make it about worker safety issues ..


https://youtu.be/QB45Q2_mOG0 Suspicious activity: A photo taken from Penang social activist Anil Netto's blog showing an active s..



Some representatives of the 24 residents associations and management corporations showing messages urging the state to resolve the flood...


Getting titles right in the engineering field in Malaysia

  Getting titles right in the engineering field in Malaysia ..

RECENTLY, the Institution of Engineers Malaysia (IEM) received an enquiry on the usage of the title “Engr.” for members of the institution. The title “Ir” was first introduced by IEM in the early 1970s for both the graduate and corporate members of the Inst...Getting titles right in the engineering field in Malaysia rightwaystosuccess.blogspot.com

 

 2 structures collapse due to incompetent engineers and irresponsible officer of MPPP/MBPP

 Penang has acknowledged the Hills Clearing cases reported by Penang Forum

 

Penang Forum tells Chief Minister: the unmitigated disasters on hill projects 


Wall and awning collapsed in house near construction site







Penang Island City Council, MBPP councilor Dr Lim fed up change not happening in Penang

 

Penang Forum concerns over hill clearing and floods; the Declaration & Recommendation 

 

 Penang flood aftermath: design pump system needed to drain out water, fix funding snag ...


  Long and winding road: This satellite picture from Google Earth Pro shows five planned interchanges of the Teluk Bahang-Tanjung Bun...



Humans Are Destroying the Environment   PETALING JAYA: They are supposed to be guardians of the environment, and yet “certain enforcem...


LATELY, we have been seeing many photographs and a lot of video footage of handcuffed men and women in orange T-shirts bearing the wor...




IJM and Genting excluded from investments wealth fund due to severe environmental damage
Environmental issues: IJM and Genting have interests in palm oil operations. Norwegian fund to call off investments on environmental iss...


PETALING JAYA: Some RM40mil from the Skills Development Fund Corp is believed to have been siphoned off by those tasked with utilising it.

Getting titles right in the engineering field in Malaysia

Sunday, 27 August 2017

Corruption has no place in any culture


LATELY, we have been seeing many photographs and a lot of video footage of handcuffed men and women in orange T-shirts bearing the words “Lokap SPRM”.

These are people who have been arrested by the Malaysian Anti-Corruption Commission (MACC) in connection with its investigations. Lokap SPRM is the Bahasa Malaysia term for the MACC lock-up.

Some of these men and women have been or will be charged in court for offences such as offering or soliciting bribes and abuse of power. If they are guilty, they will be punished.


But what if the wrongdoing is partly to do with how the private sector operates?

If businessmen believe that greasing someone’s palm is an acceptable way to get ahead of the competition, and if a company’s culture tolerates or even encourages corrupt practices, why should the employees be the only ones held accountable when the authorities enforce the law?

It is not easy, however, to prove that a company has criminal intent.

This will matter less if there are provisions in the law that deem companies responsible if employees commit certain offences in the course of their work.

This concept of corporate liability for the crimes of employees has been introduced in countries such as the United States, Britain and Australia.

Malaysia has long talked about introducing such provisions.

In July 2013, for example, Minister in the Prime Minister’s Department Datuk Paul Low said the Government wanted to introduce a “corporate liability law”.

The idea is to hold boards of directors and CEOs of companies responsible for bribes given by their employees unless it is proven that there are measures in place within the organisation to prevent corruption.

Since then, Low and senior MACC officers have several times brought up this matter.

It appears that the plan is to either amend the MACC Act or to come up with a fresh piece of legislation.

At one point, Low said the Bill would be tabled by March this year and that the new provisions would come into effect in 2018.

However, the draft legislation has yet to reach Parliament.

The latest update was from MACC deputy chief commissioner (operations) Datuk Azam Baki, who was quoted in a Sin Chew Daily report this week saying that the Cabinet had approved the Bill for the Corporate Liability Act and that it would be tabled in October.

It is understandable if the business community is less than enthusiastic about this.

There is always the fear that an employer will be unfairly blamed for an employee’s lack of integrity.

There is also the well-worn argument that complying with additional rules and regulations will increase costs amid already challenging conditions.

It is likely, however, that the new provisions are applicable only if the companies cannot demonstrate that they have done all they can to prevent the offences, or if they are negligent in addressing the risks of such offences being committed.

We will have to wait and see.

Meanwhile, businesses should examine their practices and procedures.

It is definitely in the best interest of a company to ensure that its employees understand well that corruption is not part of its corporate culture.

For that matter, corruption should not be part of any culture.

- Sunday Star Says



Amend MACC Act to give it more bite


TRANSPARENCY International Malaysia (TI-M) hails the call by the Malaysian Anti-Corruption Commission (MACC) to amend Section 23 of the MACC Act 2009 to give it greater clarity so that corrupt practices and other related offences could be better tackled especially in state-owned enterprises (SOEs).

As stated by MACC deputy commissioner (Operations) Datuk Azam Baki, MACC needs more bite to act against corrupt public officials including ministers, assemblymen and politicians.

TI-M also supports MACC on the recently proposed new law known as “Misconduct for Civil Service Act”, where civil servants who caused substantial financial losses to the Government due to negligent acts or non-compliance with official policies or procedures would face criminal charges under this proposed new Act.

TI-M has been advocating for these amendments to the existing MACC Act for the past several years and hopes to finally see the light at the end of the tunnel.

Section 23 of the MACC Act 2009 prohibits “an officer of a public body” or public officials from abusing their power for any gratification for themselves or for their relatives. TI-M shares Azam’s opinion that many politicians are being appointed into SOEs and public interest entities (PIEs).

In addition, TI-M is also looking forward to the inclusion of the corporate liability provisions into the MACC Act 2009, which will ultimately hold companies accountable for corruption cases involving their employees.

Currently, when an employee is caught for corruption or bribery, he or she will face the consequences and can be charged individually. The company which the respective employee works for is not held liable for its employees’ acts, as in law the company not being a human person is not capable of having criminal intent.

With the introduction of the corporate liability provisions, companies can be held accountable for their employees’ involvement in corruption or bribery if they are found to have failed to take adequate steps to prevent such corrupt acts by their employees.

When this becomes a reality, employers in the private sector would have no choice but to initiate anti-corruption programmes in their companies/organisations to mitigate and eventually eradicate corrupt practices.

TI-M, meanwhile, has been encouraging companies in the private sector to adopt the ISO 37001 Anti Bribery Management System as an initiative to put in place all the preventive controls and systems while simultaneously getting the top management to commit to the elimination of any form of bribery in their organisations.

On the proposed Misconduct for Civil Service Act, any effort or law to address misconduct which results in loss of taxpayers’ money should be lauded.

However, we would like to raise the issue of whether the proposed law should only apply to civil servants. What about instances where orders or instructions come from politicians or persons in elected positions? Should they not also be held liable if proven to be involved?

Any proposed law should fairly apply to everyone involved in the decision-making process, and that includes politicians.

Azam has been reported saying that each year, the AuditorGeneral’s Report reveals a litany of malpractices among government departments and agencies, some of which are outrageous, for which the civil servants responsible should be charged with criminal offences instead of just disciplinary action under the domestic rules applicable to them.

TI-M supports these new measures proposed by the MACC and hopes that the Government will give due consideration and also fully support the same by effecting the necessary changes in the law. This would ensure that we plug the existing loopholes in our anti-corruption laws.

DATUK AKHBAR SATAR President Transparency International Malaysia

 

Related Links:

 

MACC to meet on Sept 4 over CM's refusal to apologise

 

MACC questions ex-MPSP president - Nation 

 

MACC wants more muscle - Nation

 

Lim must apologise, says MACC 

 

MP defends Lim's MACC remarks - Nation

 

MACC's threat of legal action on Guan Eng an unhealthy development

 

Unisel employees pledge support for MACC probe - Nation

 

MACC reaffirms stand to stop graft, urges people to follow suit - Nation

 

Unisel employees pledge support for MACC probe - Nation

 

MACC reaffirms stand to stop graft, urges people to follow suit - Nation

 

We are not harassing Selangor, says MACC chief

 

MACC formulating new law to tackle financial misconduct in the civil service

 


Related posts:


MACC raids Unisel, MBI and contractor's office ... - The Sun Daily MACC officers conducting raids on University Selangor, Shah Al...


GEORGE TOWN: A non-governmental organisation has lodged a report with the Malaysian Anti-Corruption Commission (MACC) against two Penang...


Malaysia Anti-Corruption Commission (MACC) will call up Penang Chief Minister Lim Guan Eng and  


https://youtu.be/TpHEBW1dEmM https://youtu.be/i28FwI4tlV4 Arrest linked to illegal operation of carbon filter factory i...


More big corrupt officials nabbed: Datuk among those busted for graft & mismanagement 

 

MACC starts probe on Felda Global Ventures Holdings Bhd (FGV)

 

Making the corrupt fear whistleblowers, not the other way ! 

 

The Malaysian Anti-Corruption Commission (MACC) needs strong finishing

 

Reporting an offence is not defamation

Thursday, 24 August 2017

Graft-busting to expand after Selangor Unisel deal and Penang cases

MACC raids Unisel, MBI and contractor's office ... - The Sun Daily

MACC officers conducting raids on University Selangor, Shah Alam on Aug 22, 2017. — Sunpix by Zulfadhli Zaki

KUALA LUMPUR: After Penang and Selangor, more states can expect to come under the scrutiny of graft-busters.

“It has been ‘hot’ these days. What other states after this? Let’s wait and see,” hinted Malaysian Anti-Corruption Commission (MACC) chief commissioner Datuk Dzulkifli Ahmad during his speech at the launch of a play, Bahara Emas, which will be held from October to December nationwide in conjunction with the commission’s 50th anniversary.

He said more arrests and charges against the corrupt would take place from now until the end of the year, adding that the days were numbered for those still blinded by material possessions and money.

On allegations that the MACC’s actions on certain parties were “planned”, Dzulkifli stressed that they were not biased in their investigations.

“We don’t choose our targets. Whoever it is, whether they are politicians, civil servants or corporate figures, we will take action.

“Once a report is received and we have determined that it has a strong basis, we will carry out raids and seize documents.

“Once there is enough evidence, only then will we make arrests,” he said, adding that proper planning must be done before his officers moved in “at the right time”.

Earlier in his speech, Dzulkifli revealed his inspiration to make weekly arrests came from a 2015 Indian action movie called Gabbar Is Back, depicting the protagonist’s mission to rid corrupt officials.

“We want to empower the people to stand up and say no to corruption.

“Why? Because the MACC is here with you.

“We are the people’s voice and machinery,” he said.

Citing a case in Penang which caused pollution and another in Pahang over illegal bauxite mining, Dzulkifli said these cases happened due to issues of corruption and abuse of power.

He pointed out that those greatly affected by corruption were the people and not the ones in power, which was why “the MACC is here to carry out a probe”.

By Royce Tan The Star

MACC probes Unisel campus


https://youtu.be/mIm_G7qThN8

https://youtu.be/5W3_23yINK0

SHAH ALAM: The Malaysian Anti-Corruption Commission (MACC) is currently conducting a raid at Universiti Selangor (Unisel) in Section 7 here.

Six uniformed officers from the national anti-graft body arrived at the campus here at 9.50am on Tuesday in two separate vehicles.

Upon entering the campus' administrative building, the officers were greeted by staff members who brought them up to the offices.

The MACC is simultaneously raiding four other offices of Unisel, Mentri Besar Incorporated (MBI) and Jana Niaga Sdn Bhd offices in connection with the case.

Several uniformed officers from the MACC going in to the Unisel main campus' administration office at 11.10am.

Uniformed MACC officers were also at the Unisel main campus in Bestari Jaya.

They are currently conducting a raid at the university's administration office which is located inside the library building.

Three officers, meanwhile, arrived at the Mentri Besar Incorporated (MBI) office at Bangunan Darul Ehsan, in Shah Alam to conduct a raid.

In KUALA LUMPUR, anti-graft officers are raiding a Jana Niaga office on Jalan 4/76C.

Four officers arrived at 10.25am in a vehicle with heavily tinted windows to conduct the raid.

It is believed the MACC is acting on a report lodged with it against Selangor Mentri Besar Datuk Seri Azmin Ali and MBI over a dispute between Unisel and its contractor Jana Niaga.

It had been reported that Jana Niaga allegedly received monetary compensation and a new contract from Unisel, despite failing to complete a previous contract.

Source: The Star by danial albakri, m. kumar, andallison lai

Commission raids Unisel, MBI and contractor’s premises to investigate RM16mil payment


SHAH ALAM: The Malaysian Anti-Corruption Commission (MACC) carried out simultaneous raids on five locations in Selangor and Kuala Lumpur in its probe of RM16mil allegedly paid by a Selangor government-owned company to a private firm for maintenance work.

The places raided included the Universiti Selangor (Unisel) main campus and office, two offices belonging to the contractor – Jana Niaga Sdn Bhd – and the Menteri Besar Selangor Incorporated (MBI) office.

In all, officers took away 10 boxes and one suitcase filled with documents relating to the payment made by MBI to Jana Niaga for maintenance work of student accommodations at the Unisel main campus in Bestari Jaya.

MACC officers leaving the Jana Niaga office in Desa Pandan after the raid. Jana Niaga was responsible for maintenance work on student accommodations at the Unisel main campus in Bestari Jaya.

Sources said MBI had allegedly made the payment to Jana Niaga via two transactions of RM10mil and RM6mil in 2015 and 2016 respectively.

Initial reports received by MACC showed that MBI had paid Jana Niaga even though its contract had been terminated by Unisel.

The sources added that the MACC probe focused on the reasons why the payments were made even though Jana Niaga had failed to fulfil the contract agreement for the work done in Unisel in 2012.

MACC director of investigations Datuk Simi Abd Ghani said the investigating teams seized documents related to the case from the different locations.


“We’re still in the early stage of our investigations and we will gather strong and sufficient evidence before we proceed,” he added.

MACC officers raided the Unisel main campus in Bestari Jaya and office here, Jana Niaga’s offices in Desa Pandan and Bestari Jaya, and MBI’s office in Bangunan Darul Ehsan here.

At the MBI office, five MACC officers started their inspection at 10.45am and left at 5.50pm with a medium-sized suitcase and a box filled with documents.

Four boxes of documents were taken from the Unisel Treasurer’s office in Section 7 here at 4.30pm after the officers spent nearly seven hours there.

Other MACC officers also went to the Unisel main campus in Bestari Jaya, Kuala Selangor, and left with three boxes of documents at 4.50pm.

A Unisel spokesman said it would give its fullest cooperation to the MACC investigation.

In Kuala Lumpur, four uniformed officers went to Jana Niaga’s office in Jalan 4/76C in Desa Pandan at 10.25am and left carrying two large boxes of documents at 4.26pm.

When approached, one of the officers said the documents were from 2011 onwards. - The Star

Related Link:

Azmin not involved in Unisel agreement, says MBI officer


   Zip your lip, says MACC

Those involved in ongoing corruption cases have been warned by the Malaysian Anti-Corruption Commission not to make public statements. Its chief commissioner Datuk Dzulkifli Ahmad said such acts can be deemed as interfering with investigations and are pun


Penang cases:
Related posts:

https://youtu.be/TpHEBW1dEmM https://youtu.be/i28FwI4tlV4 Arrest linked to illegal operation of carbon filter factory i...



Malaysia Anti-Corruption Commission (MACC) will call up Penang Chief Minister Lim Guan Eng and Penanti assemblyman Dr Norlela Ariffin t...



Fall from grace: Lim, who is facing two charges of corruption alongside businesswoman Phang (left), will continue as Chief Minister with...

Tuesday, 22 August 2017

NGO alleges abuse of power by MBPP councillors


GEORGE TOWN: A non-governmental organisation has lodged a report with the Malaysian Anti-Corruption Commission (MACC) against two Penang Island City Council (MBPP) councillors for alleged abuse of power.

Persatuan Surplus Pulau Pinang chairman Sophian Mohd Zain urged the commission to probe the matter thoroughly.

He said the first case involved councillor Sharuddin Shariff who lives in a public housing unit in Sungai Pinang despite receiving a monthly allowance of RM4,000 from the council.

"This is not right at all," he said before lodging the report accompanied by former MBPP councillor Syazwani Mohd Amin.

Sophian also lodged another report against councillor Azrizal Tahir whom he alleged held two state-appointed posts.

He said Azrizal as a councillor should not have held the Village and Security Development Committee (JKKK) post and receive allowances from both positions.

When contacted, Azrizal urged the complainant not to trouble the MACC by asking them to probe cases with no basis.

He said those who lodge such reports should do their homework first.

"A press conference will be arranged to explain the matter soon," he said briefly.

Source: Edmund Lee newsdesk@thesundaily.com

MACC reports filed against PKR duo


GEORGE TOWN: Two PKR’s Penang Island city councillors have denied any wrongdoings as alleged by two non-governmental organisations which lodged reports with the state anti-graft body.

One of them, a four-term councillor, said there were no rules or regulations to prevent a councillor from becoming a village development and security committee (JKKK) chairman.

“But under a state policy which was enforced last year, we were advised not to hold the two positions at the same time.

“I have since let go of my JKKK post. I urge the complainants to check with the district office first and not to hurl baseless allegations against us,” he said when contacted.

Earlier, two NGOs – Persatuan Kebajikan Surplus Pulau Pinang and Kota – lodged reports with the Penang MACC over the alleged wrongdoings of the two councillors in Jalan Sultan Ahmad Shah yesterday.

Persatuan Kebajikan Surplus chairman Sophian Mohd Zain claimed one councillor was the JKKK chairman of Permatang Damar Laut.

“A councillor receives allowance from the local government while a JKKK post is appointed by the state government. This is a conflict of interest.

“We hope the state government will clear the air in the name of CAT (Competency, Accountability and Transparency),” he said.

Also present was former councillor Noor Syazwani Md Amin, who was terminated from her post in April.

Sophian also claimed that a first-term councillor still had a People’s Housing Programme (PPR) flat in Sungai Pinang despite having an allowance of RM4,000.

The maximum eligible household monthly income for a PPR applicant is RM2,500.

A councillor is entitled up to RM1,200 in allowances for attending meetings and a RM300 mobile phone subsidy.

“How could he still be holding the key to a PPR flat for a RM100 monthly rental? The PPR flats are meant for the poor.

“The councillors are the policy makers in the local government while the PPR flats are under the purview of the council.

“I don’t think the council staff would dare to act against the councillors,” he added.

Sophian hoped the MACC would investigate the matter.

The said councillor could not be reached for comment.

Source: by Tan Sin Chow he Star

Related Links:

MACC obtains 4-day remand against real estate developer
 Nancy: Mohd Isa still SPAD chairman

Related Posts:

Councillors ready to serve Penangites to make a difference?



  New Mayor for Penang Island City Council

The Seberang Perai Municipal Council (MPSP) president will replace outgoing Mayor Datuk Patahiyah Ismail whose contract ends on June 30 th...